Rule Change: RC_2009_03

  • Type: Standard Rule Change Process
  • Submitter: System Management
  • Title: Provision of Intermittent Generator Forecast Information
  • Market Rules Affected: Clause 7.2.5
  • Date Submitted: 16 February 2009
  • Date First Published on the IMO Website: 18 February 2009
  • Current Status: The Amending Rules commenced at 8:00am 1 July 2009.
EventDateComments
Notification Published18/02/2009 
First Submission period18/02/2009 – 1/04/2009The submission period is 6 weeks from the date the IMO published the notification
Draft Report published22/04/2009Must be published within 20 B-Days after the end of the submission period
Second submission period23/04/2009 – 21/05/2009The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published19/06/2009Must be published within 20 B-Days after the end of the second submission period
Rule Commencement01/07/2009 

Documents related to this change proposal

Submissions received in the first submission period

Submissions received in the second submission period