Rule Change: RC_2007_18

  • Submitter: Independant Market Operator
  • Title: Non Temperature Dependent Loads Timelines
  • Market Rules Affected: 4.28.8
  • Date Submitted: 13 September 2007
  • Date First Published on the IMO Website: 17 September 2007
  • Date Final Report Published: 17 January 2008
  • Current Status: Closed. The amendments to the Market Rules commenced on 1 February 2008

Timeline for this change

EventDateComments
Proposal Received by IMO13-09-2007 
Notification Published17-09-2007 
First Submission period17-09-2007 – 29-10-2007The submission period is 6 weeks from the date the IMO published the notification
Draft Report published26-11-2007Must be published within 20 B-Days after the end of the submission period
Second submission period26-11-2007 – 24-12-2007The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published17-01-2008Must be published within 20 B-Days after the end of the second submission period
Rule Commencement01-02-2008 

Documents related to this change proposal

Submissions received in the first submission period

file type icon

Alinta [645kB]

file type icon

Synergy [40kB]

Submissions recieved in the second submission period

file type icon

Alinta [320kB]