Rule Change: RC_2009_02

  • Type: Fast Track Rule Change Process
  • Submitter: IMO
  • Title: Update to Protected Provisions
  • Market Rules Affected: Clause 2.8.13
  • Date Submitted: 14 January 2009
  • Date First Published on the IMO Website: 22 January 2009
  • Current Status: The amending rules commenced at 8:00am 27 April 2009.

Timeline for this change

EventDateComments
Proposed Received by IMO14/01/2009 
Notification Published22/01/2009 
Requests to be consulted30/01/2009The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period23/01/2009 – 13/02/2009Must be completed within 15 B-Days from the date the notification is published
Final Report Published20/02/2009Must be published within 20 B-Days from the date the notification is published
Ministers Approval23/03/2009Clause 2.8.13 is a protected provision and any amendments require approval by the Minister
Rule Commencement27/04/2009 

Documents related to this change proposal

Requests to be consulted

file type icon

Synergy [40kB]

Notice on Commencement

The Minister approved the proposed Amending Rules on 15 March 2009 in accordance with clause 2.8.5 of the Market Rules.